13 February 2012
Member Present
Wilfred Kok Jia Qiang
Mark Yuen Leen Jin (Secretariat)
Khant Kyaw Nyein
Sin Cheong Loong
Eugene Zhuang
Agenda
1) To upkeep the progression of the group members
- The meeting began with Kyant updating the group that the multi threading coding is working and needs the back end coding to incorporate it with.
- The user interface is finalize as stated by Cheong Loong, but might be open to any changes if required.
- He also state that the back end coding is progressing and its pending.
- Wilfred has implemented the charting control to the prototype and has made progress, he did state that some errors occurred and will try to remedy it before the week.
- Mark and Eugene are gathering information for documentation and have decided to update the website with the relevant data.
- The group agreed to compile the program by the end of the week if possible.
- After which, the meeting is adjourned.
Vetted By Secretariat
Mark Yuen Leen Jin
No comments:
Post a Comment